Tendering re-starts for £120 million Sellafield buildings

Tendering re-starts for £120 million Sellafield buildings

Sellafield Ltd, operators of the nuclear waste decommissioning facility at Sellafield in Cumbria, have started the process of finding a contractor for its part completed £250 million waste store building project.

 

Tenders for completion of the Box Encapsulation Plant Product Store (BEPPS), Direct Import Facility and a Service Building have to be submitted by 7 April via an e-tendering portal. 

 

An earlier attempt to retender the project, which has been under way since 1997, was abandoned last year due to lack of interest from contactors in taking on the half finished project which has been scaled back from an original estimated £250 million to around £120 million.

 

The development is designed to encapsulate intermediate level nuclear waste in cement above ground in the buildings. The decommissioning task at Sellafield is said to be the most technically difficult and challenging in the world’s nuclear industry.

 

Technical uncertainties on the controversial scheme being undertaken by a Jacobs, Atkins and Carillion joint venture, led to it being stopped after five years of work in 2002.

 

Balfour Beatty and Babcock were awarded the early contractor engagement phase of the project in 2010 but rising costs led Sellafield to scale back the plans now estimated to be worth £120 million. Lack of interest last year meant the procurement process went no further than an attempted prequalification but Sellafield thinks sufficient interest now exists to attract competing bids.

 

The management of Sellafield’s decommissioning activity was contracted by the Nuclear Decommissioning Authority in 2008 to Nuclear Management Partners Ltd, a consortium of URS, AMEC and Areva, for an initial five years, which was extended for another five years in October last year. 

 

Photo: Sellafield Ltd

Please rate

Comments 

Name
Email
  Ctrl + Enter

Most Read

The government has cut £1bn from the rail infrastructure budget

The government has cut £1bn from the rail infrastructure budget

Rishi Sunak had previously promised record infrastructure investment as part of the government's "levelling up" agenda. Until now, Network Rail's "enhancement" budget for the five year period from 2019-24 had been set at £10.4bn. But, this week rail minister Chris Heaton-Harris said

Farringdon-first Central London station to complete construction

Farringdon-first Central London station to complete construction

Construction work at Crossrail’s Farringdon station has come to an end.The station becomes the first central London station along the new line to reach the T-12 landmark; this means the station is substantially complete and it is now considered to be 12 weeks away from handover to

TfL allocates extra cash to fix ageing bridges and tunnels

TfL allocates extra cash to fix ageing bridges and tunnels

Of that, TfL’s major asset renewals programme will receive a £135M additional investment to repair key bridges and tunnels. TfL figures show that about 200 out of 500 bridges and other structures that it maintains in the capital have sections in "poor" or "very poor" condition. The

This website uses cookies to enhance your user experience. By continuing to use this site, you consent to our use of these cookies. See our Cookie Policy.