'World's biggest wind farm' plans scaled back

'World's biggest wind farm' plans scaled back

Plans to build a 300 turbine wind farm at Triton Knoll 20 miles off the Lincolnshire coast have been scaled back by as much as 50% by developer RWE Npower Renewables.

 

The original £3.6Bn project was hailed as the world's biggest offshore wind farm when it was given the go ahead by the Department for Energy and Climate Change in July 2013 but RWE says it will now build capacity for between 600 and 900 megawatts rather than the original 1200 maximum. Original plans meant that the development would create 500 UK jobs during construction and up to 325 UK jobs during operation.

 

In November RWE cancelled the technically challenging £4Bn Atlantic Array wind farm off the Bristol Channel, a decision which was blamed at the time partly on government giving mixed signals about its support for offshore wind developments. RWE is Germany's second largest utility operator, behind EON SE. German utility operators have been taking actions to bolster their balance sheets after sharp falls in wholesale electricity prices that have made many German power plants unprofitable.

 

The original design for Triton Knoll envisaged a maximum of 288 turbines being installed, up to 220 metres in height. RWE says the new capacity wind farm would still be able to produce enough energy for between 550,000 and 8000,000 households.

 

The project is designed as two packages, one for the offshore array and one for the electrical system which includes a substation, underground cables and an onshore electrical compound. The new design reduces the footprint of the onshore substation by 50% and an intermediate electrical compound by 40%.

 

Some £18 million has already been invested in the project, says RWE, and a substantial proportion of contracts associated with the development will still be placed with UK companies.

 

RWE says the revised design will ensure that the efficiency and utilisation of the site is maximised. Project Manager Jacob Hain said: “The recent optimisation work is part of a project review to make the site more competitive and more economic in line with Government proposals to bring down the cost of offshore wind.”

 

Photo: Shutterstock

Please rate

Comments 

Name
Email
  Ctrl + Enter

Most Read

CONTRACTOR NAMED FOR £56M RAILWAY STATION PROJECT

CONTRACTOR NAMED FOR £56M RAILWAY STATION PROJECT

A contractor has been named to transform a major railway station in Birmingham. West Midlands Combined Authority has appointed VolkerFitzpatrick to undertake the detailed design and build of the new £56m University Station. University Station in Vincent Drive, Edgbaston, has been earmarked

DfT committs £60m funding for A361 North Devon Link Road

DfT committs £60m funding for A361 North Devon Link Road

The Department for Transport (DfT) has committed £60m in funding for the A361 North Devon Link Road widening project in the South West. Works include widening of three sections of the Link Road, covering 7.5km, to create three traffic lanes, two in one direction and one in the other

Government commits to funding Crossrail completion

Government commits to funding Crossrail completion

The project has been beset by a series of delays and cost overruns, raising concerns over its delivery. The decision to finance the completion of the project was confirmed in the government’s National Infrastructure Strategy, which insists levelling up the rest of the UK should not mean

This website uses cookies to enhance your user experience. By continuing to use this site, you consent to our use of these cookies. See our Cookie Policy.