Subsea cable contracts awarded

Subsea cable contracts awarded

Contracts valued at £27 million have been awarded by BT for what it says is its biggest ever subsea engineering project in UK territorial waters, bringing high speed broadband services to the Scottish islands.

 

Three companies have been given the work of laying subsea high speed fibre optic cables under the Minch from Ullapool on the Scottish mainland to Stornoway in the Western Isles. Chelmsford based Global Marine Systems will carry out detailed marine route surveys and supply the cables; French company Orange Marine will lay some 250 miles of subsea cable; and Hampshire based A-2-Sea Solutions will carry out related onshore works to connect the cables to BT’s terrestrial network.

 

The main cable will run for almost 50 miles and there will be 20 shorter cables connecting other areas of the Hebrides and the Northern Isles.

 

The contracts are part of a £146 million investment agreed between BT and development agency Highlands and Islands Enterprise (HIE) earlier this year to bring high speed broadband to communities throughout the north of Scotland. The project is led by HIE and is being delivered by BT, with £126.4 million of public money and £19.4 million from BT.

 

Some 84% of Highlands and Islands homes and businesses are to have access to the latest high speed fibre optic broadband by the end of 2016.  The overall project will involve laying more than 497 miles of cable on land and about 250 miles of subsea cable. Bringing broadband to the Highlands and Islands has been called one of the most ambitious infrastructure projects in Scotland’s history, seen by the Scottish government as providing a platform for economic development and regeneration.

 

BT Scotland director Brendan Dick said: “The size of the task presents a massive challenge, not only because of the number of cables involved but also the fact that the work has to be completed within a single, six month weather window.

 

“The pressure is on but we’re confident that in just over a year’s time the Highlands and Islands will be set to benefit from its own network of underwater, fibre optic cables.”

Please rate

Comments 

Name
Email
  Ctrl + Enter

Most Read

The government has cut £1bn from the rail infrastructure budget

The government has cut £1bn from the rail infrastructure budget

Rishi Sunak had previously promised record infrastructure investment as part of the government's "levelling up" agenda. Until now, Network Rail's "enhancement" budget for the five year period from 2019-24 had been set at £10.4bn. But, this week rail minister Chris Heaton-Harris said

Farringdon-first Central London station to complete construction

Farringdon-first Central London station to complete construction

Construction work at Crossrail’s Farringdon station has come to an end.The station becomes the first central London station along the new line to reach the T-12 landmark; this means the station is substantially complete and it is now considered to be 12 weeks away from handover to

TfL allocates extra cash to fix ageing bridges and tunnels

TfL allocates extra cash to fix ageing bridges and tunnels

Of that, TfL’s major asset renewals programme will receive a £135M additional investment to repair key bridges and tunnels. TfL figures show that about 200 out of 500 bridges and other structures that it maintains in the capital have sections in "poor" or "very poor" condition. The

This website uses cookies to enhance your user experience. By continuing to use this site, you consent to our use of these cookies. See our Cookie Policy.