Network Rail confirms date to reopen all four lines through Hook

Network Rail  four lines through Hook

Engineers working to repair a huge landslip at Hook in Hampshire for the purpose of reopening all four lines by Friday 24 February.

 

Following the landslip, it was only possible to run one train every 90 minutes between Basingstoke and Woking. A short time later, Network Rail took the unusual step of reconfiguring the track layout onto a stable section of the embankment to enable six trains an hour to run through the area.

 

Although this has provided an improved train service over the past few weeks whilst the embankment repairs continued, it means our engineers need to close the railway again once the embankment is repaired to reinstate the track layout to its original position.

 

What does it mean for customers?

 

  • Once the embankment repairs are completed, from the start of service on Monday 13 February, trains travelling towards Basingstoke can call at Hook again. Trains will continue to run at a reduced frequency.

 

  • From Monday 13 February until Thursday 23 February, engineers will close the railway between Farnborough and Basingstoke early each night to restore the track layout, which means alterations to late night and early morning services.

 

  • The last through services between London Waterloo station and Basingstoke (stopping), Portsmouth Harbour via Eastleigh, Salisbury and Weymouth will depart much earlier than usual.

 

  • South Western Railway (SWR) is securing rail replacement buses to operate between Woking/Farnborough and Basingstoke after 10pm each evening.

 

  • Services for Monday 13 to Friday 17 February will be updated in Journey Planners by the morning of Friday 10 February. Services from Saturday 18 to Friday 24 February are being finalised and will be updated as soon as possible.

 

  • Customers are asked to check before they travel and allow extra time to complete their journeys.

 

  • From Friday 24 February, all four lines will reopen, and the full timetable will be reinstated, however Network Rail engineers and SWR will work hard to reinstate some services sooner, if possible.

 

Mark Killick, Network Rail’s Wessex route director, said: “We’d like to thank customers and residents living alongside the railway for their patience while we’ve carried out this major repair.

 

“Fixing the landslip at Hook has been an incredibly tough and complicated job. I’m so sorry our customers will have to endure more disruption before we can reopen all four lines. Unfortunately, there is no perfect solution, but this approach is the least disruptive to our customers overall.

 

The slip, on an embankment to the northeast of Hook station, happened on Saturday 14 January, and left only two tracks of the four-track railway passable by trains, with both tracks designed to be used by London-bound trains only.

 

The landslip is in such a remote location that engineers needed to build a 580-metre-long access road across fields to get materials and machinery to the site, before the repair work could even begin.

 

Engineers are building a 60-metre retaining wall, made up of one hundred 12-metre long ‘sheet piles’ which are driven into the ground to stabilise the embankment and protect the railway from future landslips. As well as using 9,000 tonnes of stone in the repair, they will also regrade the steepness of the embankment slope to reduce the risk of material falling.

 

Read more here

 

View latest Railway vacancies here

Please rate

Comments 

Name
Email
  Ctrl + Enter

Most Read

Network Rail tenders £1.7bn minor works contract

Network Rail tenders £1.7bn minor works contract

Network Rail Southern Region is seeking 16 contractors for a new minor works framework.   The minor works buildings and civils framework (MWF-B&C) is divided into nine lots for unplanned, planned and cyclical maintenance works.   The £1.7bn framework is designed to align

Contractor signed for the construction of a £9m new Trent bridge

Contractor signed for the construction of a £9m new Trent bridge

A bridge is being built to connect pedestrians and cyclists in the Lady Bay area south of the river with the Trent Basin waterside housing estate on the north side of the river, close to Nottingham city centre.   It will be the first new crossing of the Trent in the city for 65 years.

Women in Rail Conference marks end of 10th anniversary celebrations

Women in Rail Conference marks end of 10th anniversary celebrations

Women in Rail (WR) marked the end of its 10th anniversary celebrations with its annual Conference on Thursday 2nd March 2023.   The hybrid event, hosted by London law firm Stephenson Harwood, brought together 120 in-person attendees and a virtual audience of almost 100. Tickets had sold out

This website uses cookies to enhance your user experience. By continuing to use this site, you consent to our use of these cookies. See our Cookie Policy.