Major LU re-signalling contract to be retendered

Major LU re-signalling contract to be retendered

A £354 million re-signalling contract on London Underground subsurface lines – said to be the biggest ever of its type in the world - will be retendered two and a half years after it was awarded to Bombardier. 

 

London Underground and Bombardier are in talks with around 100 engineers affected and are trying to help them find new jobs.

 

The Canadian company has pulled out of the contract to overhaul the signalling on some of the oldest parts of the underground claiming that its signalling system would be incompatible with the Underground’s.  London Underground has said that it needed to change contractors in order to deliver the project on or close to the original completion date.

 

Bombardier won the contract after an 18-month tendering process but London Underground says that despite having to select a new supplier the original project completion date of 2018 will still be achieved. Siemens is said to be front runner to take on the contract, but the procurement process could take until summer with LU this week seeking expressions of interest in the Official Journal of the European Union (OJUE).

 

Bombardier has already spent up to £85 million on a new unified control centre for the upgraded underground lines involved which is expected to be paid by LU. Other enabling works are also understood to have been carried out to an advanced stage.

 

The upgrade affects a number of underground lines, a total of some 40% of the system’s route miles and is to be carried out first on the Metropolitan and then the Circle Lines, followed by the Hammersmith & City and finally the District Line.  The Circle and Hammersmith & City lines will see their capacity increase by 65%, the Metropolitan Line by 27% and the District Line by 24%.   

 

Bombardier retains its contract to supply 191 trains for the upgraded lines, the S-Stock Fleet which are air conditioned and walk-through. Some of these trains are already in operation on the Hammersmith & City and Circle lines.

 

Part of the complexity of the project arises from the number of busy junctions where trains from different lines cross paths. Re-signalling these areas will shorten delays experienced while trains wait until it is safe to proceed.

 

London Underground Managing Director Mike Brown said: “We have been working closely with Bombardier to find a way forward on what is one of the most challenging and complex pieces of work on the Tube. However it has become apparent to both parties that for the work to be completed within or close to the planned deadline we need to push on with works with another contractor.” 

Please rate

Comments 

Name
Email
  Ctrl + Enter

Most Read

HS2’s longest tunnels reach halfway point under the Chilterns

HS2’s longest tunnels reach halfway point under the Chilterns

HS2 Ltd says that ‘Florence’ and ‘Cecilia’, the two giant tunnelling machines excavating the high speed rail project’s longest tunnels, have passed the halfway point on their 10 mile journey under the Chilterns.   The enormous 2,000 tonne machines have spent the

CP7 projects announced for Wales & Western region

CP7 projects announced for Wales & Western region

Network Rail has announced AmcoGiffen, Octavius, BAM Nuttall, Morgan Sindall Infrastructure, and Taylor Woodrow will be among their trusted suppliers involved in delivering Wales and Western region’s £2bn programme of works over the next eight years.   The six contracts play a

Anglian Water advances 68km water main plan

Anglian Water advances 68km water main plan

Hundreds of kilometres of new interconnecting pipelines – stretching from North Lincolnshire, through Cambridgeshire, to Suffolk and Essex – will be laid as part of the scheme.   The Bury St Edmunds to Colchester pipeline will run for 68km and includes new above-ground assets in

This website uses cookies to enhance your user experience. By continuing to use this site, you consent to our use of these cookies. See our Cookie Policy.