Major LU re-signalling contract to be retendered

Major LU re-signalling contract to be retendered

A £354 million re-signalling contract on London Underground subsurface lines – said to be the biggest ever of its type in the world - will be retendered two and a half years after it was awarded to Bombardier. 

 

London Underground and Bombardier are in talks with around 100 engineers affected and are trying to help them find new jobs.

 

The Canadian company has pulled out of the contract to overhaul the signalling on some of the oldest parts of the underground claiming that its signalling system would be incompatible with the Underground’s.  London Underground has said that it needed to change contractors in order to deliver the project on or close to the original completion date.

 

Bombardier won the contract after an 18-month tendering process but London Underground says that despite having to select a new supplier the original project completion date of 2018 will still be achieved. Siemens is said to be front runner to take on the contract, but the procurement process could take until summer with LU this week seeking expressions of interest in the Official Journal of the European Union (OJUE).

 

Bombardier has already spent up to £85 million on a new unified control centre for the upgraded underground lines involved which is expected to be paid by LU. Other enabling works are also understood to have been carried out to an advanced stage.

 

The upgrade affects a number of underground lines, a total of some 40% of the system’s route miles and is to be carried out first on the Metropolitan and then the Circle Lines, followed by the Hammersmith & City and finally the District Line.  The Circle and Hammersmith & City lines will see their capacity increase by 65%, the Metropolitan Line by 27% and the District Line by 24%.   

 

Bombardier retains its contract to supply 191 trains for the upgraded lines, the S-Stock Fleet which are air conditioned and walk-through. Some of these trains are already in operation on the Hammersmith & City and Circle lines.

 

Part of the complexity of the project arises from the number of busy junctions where trains from different lines cross paths. Re-signalling these areas will shorten delays experienced while trains wait until it is safe to proceed.

 

London Underground Managing Director Mike Brown said: “We have been working closely with Bombardier to find a way forward on what is one of the most challenging and complex pieces of work on the Tube. However it has become apparent to both parties that for the work to be completed within or close to the planned deadline we need to push on with works with another contractor.” 

Please rate

Comments 

Ctrl + Enter

Most Read

Ten highest paying I.T jobs in 2019

Ten highest paying I.T jobs in 2019

The I.T industry is arguably the most in-demand industry for technology/Engineering professionals. Once you have the right skill and certification, the I.T industry will jump at the chance to employ you and grant you a befitting role. From application developers to Data Engineers, the sector is in

H2S: It’s an exciting time to be a civil engineer

H2S: It’s an exciting time to be a civil engineer

The High Speed Two (H2S) has been described as a game-changer and the greatest ever upgrade to Britain's railways, and without doubt, this United Kingdom’s high-speed rail project has been a hot topic. The H2S project aims to meet the United Kingdom’s high

The future of engineering in Artificial Intelligence

The future of engineering in Artificial Intelligence

Artificial intelligence (AI) is an aspect of computer science that is concerned with machine intelligence. Machine intelligence can be described as the theory and development of computer systems to have the capacity to carry out tasks that would ordinarily require human input or intelligence. Some

This website uses cookies to enhance your user experience. By continuing to use this site, you consent to our use of these cookies. See our Cookie Policy.