Link road will help port to grow

Link road will help port to grow

Work will start early in the new year on the delayed £124.5 million Heysham to M6 Link Road after the Court of Appeal threw out a call for a judicial review of the Transport Secretary’s decision to approve the scheme. Around 3,000 jobs are expected to be created during construction.

 

Costain had earlier been awarded the construction contract and has been on site for some weeks getting mobilisation under way. The project, which was granted development consent in March, is a priority for Lancashire County Council. The planning process involved six months of examination of the case with three weeks of public hearings at which a campaigners group called Transport Solutions for Lancaster and Morecambe led opposition which led to a High Court challenge.

 

Following a two day hearing in July the High Court ruled against the campaigners in October, refusing permission to apply for judicial review. A final application to the Court of Appeal to reverse the High Court decision this week was also refused.

 

The road will complete a connection between the Heysham and Morecambe peninsula and junction 34 on the M6. It will be dual carriageway with a footpath and cycleway.

 

The construction works will involve remodelling junction 34, new slip roads, a new bridge over the River Lune and a park and ride site for 600 vehicles. The link will provide improved access to Morecambe and industrial areas including the Port of Heysham and the Heysham power stations. It is also designed to reduce congestion in the Lancaster area.

 

Improving links to Heysham Port which is the third largest in the north west of England is hoped to allow it to develop as a hub for services to Ireland. The port specialises in roll-on roll-off freight and is also a supply base for a major offshore gas field and wind farms. Severe road congestion is said to be acting as a barrier to growth.

 

Image: Lancashire County Council

Please rate

Comments 

Name
Email
  Ctrl + Enter

Most Read

Crossrail Elizabeth line to open on 24 May 2022

Crossrail Elizabeth line to open on 24 May 2022

The Elizabeth line will transform travel across London and the South East by dramatically improving transport links, cutting journey times, providing additional capacity, and transforming accessibility with spacious new stations and walk-through trains. The Elizabeth line will initially operate as

HS2 site acquisition paves way for Manchester high speed station

HS2 site acquisition paves way for Manchester high speed station

HS2 Ltd has reached an agreement with Bruntwood, one of the UK’s leading property providers, to purchase Square One on Travis Street in readiness for construction of Manchester’s brand new high speed railway station.   The sale marks HS2’s second major property acquisition

Alun Griffiths wins A4119 upgrade

Alun Griffiths wins A4119 upgrade

Alun Griffiths has been appointed to widen the A4119 to dual carriageway from Coed Ely to Ynysmaerdy.   The main construction phase is on course to start on site in late summer 2022.   The A4119 project is designed to improve connectivity and encourage economic activity into the

This website uses cookies to enhance your user experience. By continuing to use this site, you consent to our use of these cookies. See our Cookie Policy.