HS2 names three JVs awarded the £900m Enabling Works Contracts

HS2 names three JVs awarded the £900m Enabling Works Contracts

With a two-month delay, HS2 has finally confirmed the three joint ventures that will deliver the necessary pre-civil engineering works of HS2 Phase One from London to Birmingham. These works will predominantly be related to archaeology, site clearance and other site compounds preparations.

 

The following joint-ventures have been appointed to convey the £900m Enabling Works Contracts:

- Costain Group Plc and Skanska Construction UK Ltd (CS JV) will work together on the South Area

- Morgan Sindall plc, BAM Nuttall Limited and Ferrovial Agroman Ltd (Fusion JV) will unite forces for the works on the Central Area.

- Laing O’Rourke Construction Ltd and J. Murphy & Sons Ltd (LM JV) will be in charge of the North Area.

 

It looks like the LM JV bid was more attractive than the one submitted by Balfour Beatty and Vinci JV, as the latter is not mentioned in today’s press release from HS2.

The three JVs will deliver a variety of activities in utilities, ecology, ground remediation, highways, instrumentation and monitoring, demolition, structural engineering and drainage.

HS2 Managing Director Jim Crawford has expressed his satisfaction today as the team moves one step closer to starting another critical phase ahead of the main construction programme.

 

The project should generate thousands of technical and engineering jobs and training opportunities in Greater London, the South East and UK-wide.

The works for Phase One of the £56bn railway are due to start in Spring 2017 with a view to open in December 2026.

 

On another note, after about two years of debates and discussions the government has also released the route for Phase Two of the HS2 line from Crewe to Manchester and from West Midlands to Leeds. Following complaints from Sheffield City Council, the newly proposed HS2 line will use the existing rail network that runs through Sheffield city centre. From now, people in affected regions can begin the process of claiming compensation by following this link.

 

The Phase Two high-speed line continuing up to Yorkshire, north-west England, and beyond, is planned to be completed by 2033.

 

Working in civil engineering? Why don't you browse our civil engineering vacancies today?

 

Sources:

www.gov.uk

www.bbc.com

www.building.co.uk

Please rate

Comments 

Name
Email
  Ctrl + Enter

Most Read

The government has cut £1bn from the rail infrastructure budget

The government has cut £1bn from the rail infrastructure budget

Rishi Sunak had previously promised record infrastructure investment as part of the government's "levelling up" agenda. Until now, Network Rail's "enhancement" budget for the five year period from 2019-24 had been set at £10.4bn. But, this week rail minister Chris Heaton-Harris said

Farringdon-first Central London station to complete construction

Farringdon-first Central London station to complete construction

Construction work at Crossrail’s Farringdon station has come to an end.The station becomes the first central London station along the new line to reach the T-12 landmark; this means the station is substantially complete and it is now considered to be 12 weeks away from handover to

TfL allocates extra cash to fix ageing bridges and tunnels

TfL allocates extra cash to fix ageing bridges and tunnels

Of that, TfL’s major asset renewals programme will receive a £135M additional investment to repair key bridges and tunnels. TfL figures show that about 200 out of 500 bridges and other structures that it maintains in the capital have sections in "poor" or "very poor" condition. The

This website uses cookies to enhance your user experience. By continuing to use this site, you consent to our use of these cookies. See our Cookie Policy.