Barhale JV wins Dewsbury sewage works upgrade

sewage works

Works at the Dewsbury plant are designed to ensure phosphorus concentrations in the final effluent meet water industry national environment programme targets for England.

 

The project forms part of Yorkshire Water’s £500m investment in phosphorous removal to meet current and anticipated Environment Agency quality targets.

 

Central to the scheme is the replacement of some of the 14 existing primary settlement tanks with three larger tanks and two primary sludge pumping stations.

 

Precast concrete wall sections will be assembled on site to form the new 8.5-metre deep, 45-metre diameter settlement tanks. An existing beck will be diverted to make way for the construction of the tanks.

 

BarhaleEnpure JV will convert one of the existing primary settlement tanks into a primary distribution chamber that will distribute flow to the new tanks. It will also install a new chemical dosing plant comprising two 40 m3 storage tanks and dosing equipment housed in a new steel-framed building that will be manufactured off-site.

 

“Effective management of phosphorous levels can make a big difference to the quality of water in our rivers and streams,” said Barhale regional director Mark Wood. “This is a major upgrade for the Dewsbury wastewater treatment works, which reflects Yorkshire Water’s ambitions for P-removal across its assets and its commitment to meet new standards.”

 

BarhaleEnpure JV framework manager Steve Milling added: “The award of this design and construct contract follows a prolonged early contractor involvement phase of more than two years. Through this period, the BarhaleEnpure JV design team worked closely with Yorkshire Water and Stantec to refine the outline design and introduce significant value engineering changes.”

 

Read more here

 

View latest Water & Utitlities vacancies here

Please rate

Comments 

Name
Email
  Ctrl + Enter

Most Read

Construction of £45m Ash bridge starts this month

Construction of £45m Ash bridge starts this month

VolkerFitzpatrick starts work this month on a £44.5m bridge construction project in Surrey.   Guildford Borough Council appointed VolkerFitzpatrick in July as main contractor for a long-planned bridge over a railway line next to Ash station.   Construction of the Ash Road Bridge

Four companies win £360m Yorkshire Highways Alliance deal

Four companies win £360m Yorkshire Highways Alliance deal

Four contractors have secured spots on a major works framework covering highways and transportation projects in Yorkshire   Balfour Beatty, BAM Nuttall, Farrans and John Sisk will deliver projects valued over £7m.   The framework firms will be used by Leeds Council and the wider

Approval for HS2’s Balsall Common Viaduct in Warwickshire

Approval for HS2’s Balsall Common Viaduct in Warwickshire

The project is being led by HS2’s main works contractor, Balfour Beatty VINCI (BBV), supported by a Design Joint Venture of Mott MacDonald and SYSTRA together with architects Weston Williamson + Partners. They have engaged with people in the local area over the last couple of years to gather

This website uses cookies to enhance your user experience. By continuing to use this site, you consent to our use of these cookies. See our Cookie Policy.