Balfour bags £52m London power tunnels project

Balfour bags £52m London power tunnels project
balfourbeatty.com

After delivering the cabling works for phase one of the London Power Tunnels project, north of the Thames, Balfour Beatty will now embark on the second phase of the ambitious scheme to ‘rewire London and connect with the capital’.

 

Works will include installing 200km of 400kV cables within a 32.5-kilometre underground tunnel network, below the ground between Wimbledon and Crayford.

 

Connecting several substations across London, the cables will run through an underground tunnel network to minimise disruption to local communities and the travelling public when future maintenance and repair works are required.

 

Expertise and innovation in tunnel cable installation

 

Balfour Beatty will deploy the second generation of its Automated Cable Installation Equipment (ACIE) machine to enhance efficiency.


Developed in-house and used on the first phase of the scheme, the second-generation machine features laser sensors and cameras to improve the speed and quality of the works.

 

By automating the process, the ACIE has also revolutionised the safety of tunnel cable installation works by reducing the number of people required within the underground tunnels manually installing the cables.

 

Ian Currie, managing director of Balfour Beatty’s power transmission and distribution business, said: “We are delighted to be working with National Grid once again.

 

“Our world-leading expertise and innovation in tunnel cable installation, combined with our deep sector knowledge, makes us ideally positioned to successfully deliver this critical piece of national infrastructure.”

 

Cable installation will begin in January 2023 with the full package of works expected to be completed in 2026.

 

At peak construction, Balfour Beatty will employ a workforce of around 150 people, as well as approximately 8 apprentices.

 

Please rate

Comments 

Name
Email
  Ctrl + Enter

Most Read

Balfour Beatty launches sustainable site cabin, EcoSense

Balfour Beatty launches sustainable site cabin, EcoSense

The cabin features a range of sustainable features such as occupier-activated extractor fan sensors and lower kilowatt heaters with built-in, self-regulating digital thermostats – reducing carbon emissions on site by up to 30%.   Environmental savings   The EcoSense model

HS2 creates first of 56 giant piers for UK’s longest rail bridge

HS2 creates first of 56 giant piers for UK’s longest rail bridge

Stretching for 3.4km, the viaduct – being built as part of the HS2 rail project – will carry high speed trains travelling at speeds of up to 200mph between the outskirts of Hillingdon and the M25 on their way to Birmingham and the north. The first pier was cast by engineers from

Turner & Townsend wins £23.3m Lower Thames Crossing contract

Turner & Townsend wins £23.3m Lower Thames Crossing contract

The award of the commercial partner marks the completion of the Lower Thames Crossing integrated client team, comprised of National Highways, a technical partner, and an integration partner.   The eight-year contract will see Turner & Townsend work as part of National Highways

This website uses cookies to enhance your user experience. By continuing to use this site, you consent to our use of these cookies. See our Cookie Policy.